7,818 consented schemes · no recorded start

LONDON HOUSING · CONSENTED BUT UNBUILT · DATA TO 2026-08-01

PERMISSION
GRANTED.
Nothing built.

London’s housing crisis is not only a planning-permission problem. 100,477 homes approved by London boroughs between 2015 and 2021 still have no recorded construction start — an average of 7.7 years after the decision. This platform maps where they are, who they were promised to, and which borough they belong to. Every figure is traceable to a published government dataset.

100,477

APPROVED HOMES WITH NO RECORDED CONSTRUCTION START (2015–21 DECISIONS)

19,988

OF THOSE HOMES WERE CONSENTED AS AFFORDABLE TENURES

15,692

HOMES BELOW REQUIREMENT ACROSS LONDON, HOUSING DELIVERY TEST 2020–23

7.7 YRS

AVERAGE TIME SINCE PERMISSION WAS GRANTED ON A STALLED SCHEME

THE MAP · FIVE VERIFIED LAYERS

Where London’s
housing stops.

Every layer is a published government figure, not a model. Boroughs are shaded by decile within London. Switch layers to compare demand, delivery, stalled consents, affordable loss and decision speed. Click a borough to filter the register below.

LOADING BOROUGH GEOMETRY…
FEWMOST STALLED

HOVER A BOROUGH TO READ ITS VALUE · CLICK TO FILTER THE REGISTER · SOURCE: PLANNING LONDON DATAHUB — RESIDENTIAL UNITS, 2015–2021 DECISIONS

PART ONEThe pipeline is full of homes nobody is building.

CONSENTED, NOT COMMENCED

100,477 homes are stuck between yes and a building site.

7,818 residential schemes approved by London boroughs from 2015 to 2021 have no commencement date recorded in the Planning London Datahub.

93,911 of those homes sat on permissions the boroughs have since recorded as lapsed — consent expired before a spade went in. A further 6,566 homes hold live permission with no start logged. Average age of a stalled permission: 7.7 years.

BRENT10,351
BARKING AND DAGENHAM10,237
NEWHAM6,681
EALING6,303
HAVERING6,122
GREENWICH6,025
PART TWOThe affordable homes are the ones that vanish.

WHO THE HOMES WERE FOR

20% of the stalled homes were consented as affordable.

19,988 affordable homes were negotiated, approved and never started.

Affordable units are usually the planning gain that justified the density. When a scheme stalls, that gain is not deferred — the permission lapses and the obligation dies with it. Meanwhile the boroughs furthest from their targets in the 2023 Housing Delivery Test were Lewisham (32%), Redbridge (39%), Greenwich (48%). A score below 75% triggers the presumption in favour of sustainable development — the government’s formal sanction for under-delivery.

PART THREESpeed is agreed away, not achieved.

THE 13-WEEK FICTION

Major applications are almost never decided in the statutory time.

Across London, only a fraction of major planning decisions land inside the 13-week statutory period; the rest run on agreed extensions that count as “on time”.

Islington decided 0% of 23 major applications inside 13 weeks, Greenwich decided 2% of 51 major applications inside 13 weeks, City of London decided 2.3% of 44 major applications inside 13 weeks (MHCLG Table P151a, April 2024 – March 2026). Because performance is measured against extensions of time, a borough can report near-perfect compliance while applicants wait years. Delay at the front door and stalling after consent are the same story told twice.

THE REGISTER · 100,477 HOMES

The stalled sites
register.

The 164 largest stalled residential schemes, with full application records retrieved from the Planning London Datahub. Stall risk score combines age of permission (40%), scheme size (30%), affordable share (20%) and the borough’s Housing Delivery Test result (10%). Click any row for a sourced evidence card.

164 SCHEMES · 64,140 HOMES · 16,348 AFFORDABLE
SITEBOROUGHHOMESAFFORDABLEPERMISSIONSTATUSSTALL RISK
Convoys WharfREF DC/13/83358 · SE8 3JDLewisham3,5005252015 PERMISSION LAPSED81
Phase 6 Kidbrooke VillageREF 14/2554/O · SE3Greenwich8461662015 NO RECORDED START76
S21: Site bounded by Royal Victoria DockREF 14/01605 · E16Newham3,0005762016 NO RECORDED START73
Barking ReachREF 16/00131/OUT · IG11 0XFBarking and Dagenham9,8913,7762017 PERMISSION LAPSED72
Gallions QuarterREF 14/00664 · E16 2BFNewham8002992016 PERMISSION LAPSED71
The Waterfront MasterplanREF 16/3025/MA · SE18Greenwich7382802017 PERMISSION LAPSED70
Green Car ParkREF 15/5550A · HA9 0DLBrent4,1151,4732016 PERMISSION LAPSED69
Land North Of Royal Albert DockREF 14/00618/OUT · E16Newham84502015 PERMISSION LAPSED67
Ruby Triangle SiteREF 18/AP/0897 · SE15 1LGSouthwark1,1524512019 PERMISSION LAPSED65
Stratford Centre and Morgan HouseREF 14/02289 · E15 1XBNewham587812016 PERMISSION LAPSED62
Land bound by Waterloo Road to the east;REF P0761.20Havering2,7601,1122021 PERMISSION LAPSED60
Former Somerfield DepotREF P1813.11 · RM13 8DEHavering49702015 PERMISSION LAPSED60
Carphone WarehouseREF P/2015/0095 · W3 6ULEaling76402016 PERMISSION LAPSED59
Former Felnex Trading Estate Site, 190REF C2016/73625 · SM6 7ELSutton7251502016 PERMISSION LAPSED59
Sainsbury's, 55REF 4499/15 · IG1 2AARedbridge683272018 PERMISSION LAPSED59

WHAT TO DO WITH THIS

Stop counting permissions.
Start counting starts.

01 · FOR BOROUGHSPublish a commencement date for every consent. 100,477 homes are invisible in the delivery pipeline because nobody recorded whether they began.

02 · FOR THE GLAReport lapsed permissions as a delivery metric. 93,911 homes expired on paper without appearing in any published shortfall.

03 · FOR CAMPAIGNERSUse the register. Each evidence card carries the reference, the tenure mix and the source dataset, so a stalled site can be raised at a planning committee without new research.